Lesson 13 Worksheets Scroll down What You Will Learn How to add Labour to a Worksheet. How to finalize job pricing. Getting Started
Lesson 1
1 Click on the Worksheets button in the Winpriser toolbar.
OR From Winprisers main menu, select the File | Open Worksheet menu option:
The Worksheet Directory dialog box will appear:
2 Select the worksheet that you created in Lesson 12 from the list of worksheet titles and click on the F2 Open
3 Select the Direct Labour worksheet view from the list of available views:
The right side of the worksheet window will look something like this:
4 The Direct Labour View is used to itemize the different types of labour, the labour charges and the labour hours involved in this job.
Click on the Add Blank
5 Enter the name of an employee who will work on this job. Press the Enter key.
6 Type the dollars per hour that you will be charging your customer for this type of labour into the Cost/Hr field. Press the Enter key.
7 Enter the number of man-hours for this labour type in the Hours Allocated field. Press Enter.
The total labour charge for this type of labour will be shown in the Ext. Cost (Extended Cost) field. 8 If you have created a Labour Rate Sheet (see Lesson 8), you can use the Add Rate Press the Add Rate button to open the Select Direct Labour window.
The Select Direct Labour window shows the available Labour Rate Sheets.
9 Click on the General Labour rate sheet that we created in Lesson 8.
10 Highlight the Labour Rate to be added to the worksheet in this case EMPLOYEE 1. Press the Ok button. The Labour Description and charge will be added to the Labour table.
11 Double click on the Hours Allocated field for EMPLOYEE 1. Enter the number of man-hours for EMPLOYEE 1 for this job and press the Enter key.
The total labour charge for EMPLOYEE 1 will be shown in the Ext. Cost field. And the total man-hours and labour charges for the job will be shown:
If you have assigned Labour Units to items in the Catalogue or if you have entered Labour Units on the Worksheet Material Extensions Labour tab, Winpriser will calculate the total man-hours based on your labour units. This total is shown by labour system in the lower left corner of the Labour table.
Winpriser does not attempt to sub-divide the total man-hours based on labour units or assign labour charges. Use the total labour unit man-hours as a guide as you assign labour types, charges and man-hours to the job as in the lesson steps above.
The Job Summary Worksheet View allows you to total materials and labor pricing and to add extra charges and/or overall markups. The result is the overall job price. 12 Select the Job Summary worksheet view from the list of available views:
The Job Summary view looks like this:
13 The material pricing for the job can be based on total Allpriser List, total Resale price, total Net price or total Trade price. Click on the down arrow beside Select Price Base and select the various price bases. Note how the Material Totals and Job Totals change.
Select Resale Price Base.14 The Job Summary View is divided into five sections Total worksheet material extension view pricing Addition material (i.e. permits, licenses) not shown on worksheet Total labour from Direct Labour view Additional labour charges not shown in Direct Labour view Taxes and Job Total 15 Click on the Materials 16 Click the Labour 17 Click on the Taxes Enter percentages into the Overhead and Markup fields and note how the totals are affected.
|
Copyright Allpriser Ltd - 2011